OGUN GOVT URGES PATIENCE AS ABEOKUTA–SANGO OTA ROAD RECONSTRUCTION PROGRESSES
Written by Oluwaseyi Amosun on October 24, 2025

Photo File: Abeokuta Sango Ota road under construction
The Ogun State Government has appealed to motorists and residents using the Abeokuta–Sango Ota Road to remain patient as reconstruction work continues along the busy route.
The state Commissioner for Works and Infrastructure, Ade Akinsanya, made the appeal in a statement he personally signed yesterday. He acknowledged that some sections of the road have become slippery due to earthworks and persistent rainfall, which have slowed the pace of work.
He explained that the ongoing casting of concrete pavement in some sections along the Ewekoro axis has led to temporary closures and traffic diversions.
Akinsanya assured the public that the government is working tirelessly to rehabilitate and fully restore the road’s viability.
“Despite the challenges posed by the rainy season, we remain committed to completing the project in record time,” he said.
The commissioner urged road users to exercise caution and obey traffic diversions, especially around the Ewekoro area where concrete casting is ongoing.
He noted that key sections such as Obada Oko, Ilese Awo, Onijanganjangan, and Ewekoro are currently receiving focused attention from the contractor to improve driving conditions and ease movement.
According to him, although the Lagos–Abeokuta Expressway is a federal road, the Ogun State Government, in line with its people-oriented policies, has taken over its reconstruction to ease the hardship faced by commuters.
He added that the intervention aims to reduce traffic congestion, shorten travel time, and prevent accidents and loss of productive hours.
Akinsanya expressed optimism that as the rains subside, the challenges currently faced by road users would ease.
He reaffirmed the government’s commitment to delivering durable and high-quality road infrastructure across Ogun State.
The reconstruction project was flagged off by Governor Dapo Abiodun in August 2024 with an 18-month completion timeline. The road had been in a deplorable state for years, causing hardship for motorists, commuters, and residents.





Eagle Fm